Quick answer: Strip footing volume = length × width × depth (all in feet) ÷ 27. A 12-inch-wide, 12-inch-deep trench runs 0.37 yd³ per 10 feet — about 17 eighty-pound bags. Piers: π × r² × depth.
10% standard · 15% broken forms
| Strip formula | L ft × W in ÷ 12 × D in ÷ 12 ÷ 27 = yd³ |
|---|---|
| Pier formula | π × (D/2)² × depth = ft³ |
| Typical deck pier | 12" dia × 48" deep ≈ 0.12 yd³ |
| Default waste | 10% |
How does the footing calculator work?
A continuous footing is just a long, narrow slab: trench length × width × depth, with width and depth in inches converted to feet. Round piers use the circle formula — π × radius² × depth. Both feed the same engine as the slab calculator, so you get cubic yards plus the 80/60/40-lb bag conversion with your waste factor applied. Typical deck footings run 10–12 inches wide and to frost depth (anywhere from 12 inches in warm regions to 48+ inches up north — check your local code); a single 12-inch pier 48 inches deep is only about 0.12 yards, which is why footings are almost always bag work.
Common uses
- Sizing deck pier bells one hole at a time
- Estimating a trench run of continuous footing
- Deciding bag count before renting a mixer
- Verifying volume against the engineer's footing schedule